After recently completing work to create eight guest rooms at Thonock Park in Gainsborough, Gelder Group are now undertaking further refurbishment works to the main building. The extensive works are being undertaken within a very tight schedule of four weeks, ensuring all work is complete in readiness for the club’s busy, winter events calendar. The works include a new storm lobby, refurbishment of the ground floor and first floor and a new reception area.
Contracts Manager for the project, Joe Allmond, commented:
With the timescales involved, there is no margin for error in this project. Thonock Park is still open and our workforce is mindful that the club is constantly in use, so health and safety is at the forefront of each section of the refurbishment. We are on schedule to complete on time and deliver the facilities the club has requested.