Yarborough Leisure Centre back open for Christmas
The 20 week schedule get to get the new lighting and ventilation system put in place was a tall order, but our commitment to the Yarborough Leisure Centre was to get them back open for January, we not only met the clients expectation but exceeded them by getting it back open before Christmas. On the […]
Work at Yarborough Leisure Centre Progressing Well
The work to install new lighting, ventilation and a new ceiling above the swimming pool at Yarborough Leisure Centre is progressing on schedule, the £500k project will take 20 weeks to complete and will be completed early next year.